Analisis Potensi Pembangkit Listrik Tenaga Mikrohidro (PLTMH) Pada Sungai Air Besar Kampung Air Besar Kabupaten Fakfak

Authors

  • Yulianto La Elo Politeknik Negeri Fakfak, Fakfak Papua Barat
  • Rusliadi Rusliadi Politeknik Negeri Fakfak, Fakfak Papua Barat
  • Zharin Fahrah Syahdinar Politeknik Negeri Fakfak, Fakfak Papua Barat

DOI:

https://doi.org/10.32492/jeetech.v4i1.4102

Keywords:

Potential of Micro Hiydro, Electricity power, River Air Besar

Abstract

Fakfak Regency, West Papua Province has a Watershed and Waterfall, the Air Besar River is one of the rivers that has the opportunity to be used as a Micro Hydro Power Plant (PLTMH). Due to the large difference in flow elevation between upstream and downstream, it is hoped that this local resource can be developed for other potentials, one of which is for Micro Hydro Power Plants (PLTMH). It is hoped that this Micro Hydro Power Plant (PLTMH) will not only be able to use water as a source of energy, but also increase profits with the availability of tourism. The purpose of this research is to detect the ability of the Air Besar River as a Micro Hydro Power Plant (PLTMH). The research method used is the floating method to determine the water rate and the cross section. Furthermore, calculations are carried out to obtain the amount of water discharge, determining the effective fall height (Heff) of the flow to obtain power and energy that can be produced by river flow while account the efficiency of the generator and turbine. From the calculation results, it is known that the large water discharge from the river is 23,826 m3/s, the effective fall height (Heff) flow is 4 m. From the results of these calculations, it is known that the estimated electrical power that can be generated is 620.8159 kW.

References

UNDESA, “The Human Right to Water and Sanitation. International Decades for Action "Water for Life" 2005-2015,” United Nation Departmen of Economic and Social Affairs, 2010.

I. M. D. a. A. Program, “Pedoman Studi Kelayakan PLTMH,” Dirjen Listrik dan Pemanfaatan Energi Depatemen Energi dan Sumber Daya Mineral, Jakarta, 2009.

G. Prayoga, Studi Potensi Pembangkit Listrik Tenaga Mikrohidro Head Rendah di Sungai Cisangkuy Kabupaten Bandung (Kajian Teknis), Bandung: ITB, 2008.

A. Lesmana, Studi Potensi Pembangkit Listrik Tenaga Mikrohidro Head Rendah di Sungai Cisangcuy Kabupaten Bandung (Kajian Ekonomis), Bandung: ITB, 2008.

S. P. Putra, Studi Potensi Saluran Irigasi Cipaganti dan Cibarani Bandung sebagai Pembangkit Listrik Tenaga Micro-Hydro, Bandung: ITB, 2008.

M. D. T. Sogen, “Studi Perencanaan Pembangunan PLTMH di Kampung Sasnek Distrik Sawiat Kabupaten Sorong Selatan Provinsi Papua Barat,” Jurnal ELECTRO LUCEAT (JEC), vol. 3, no. 1.

T. Marhendi dan Toifin, “Studi Potensi Pembangkit Listrik,” 2019.

T. M. Toifin, “Studi Potensi Pembangkit Listrik Tenaga Mikro Hidro di Sungai Brukah (Kali Bening, Banjarnegara),” Jurnal Techno, vol. 20, no. 1, 2019.

M. Hasib Al Isbilly, Markhaban Siswanto, and Machrus Ali, “Optimasi PID Kontroller Pada Sistem Pengaturan Irigasi Menggunakan Metode Bat Algorithm,” J. JEETech, vol. 3, no. 2, pp. 78–83, Oct. 2022, doi: 10.48056/jeetech.v3i2.198.

M. Ali, M. R. Djalal, S. Arfaah, Muhlasin, M. Fakhrurozi, and R. Hidayat, “Monitoring and Identification Electricity Load Using Artificial Neural Network,” in 2021 7th International Conference on Electrical, Electronics and Information Engineering (ICEEIE), IEEE, Oct. 2021, pp. 1–6. doi: 10.1109/ICEEIE52663.2021.9616922.

Published

2023-02-06

How to Cite

[1]
Y. La Elo, R. Rusliadi, and Z. Fahrah Syahdinar, “Analisis Potensi Pembangkit Listrik Tenaga Mikrohidro (PLTMH) Pada Sungai Air Besar Kampung Air Besar Kabupaten Fakfak ”, jeetech, vol. 4, no. 1, pp. 9-14, Feb. 2023.

Issue

Section

Articles